Solar project G0589, Klickitat County

Solar project G0589, Klickitat County is a 381 MW solar request in interconnection study in the West interconnection queue, in Klickitat County, Washington.

Queue statusIn planning
  1. PlanningQueued May 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G0589
Grid region
West (non-ISO utilities)
Connection point (POI)
Knight 500 kV Substation
Location
Klickitat County, Washington
Technology
Solar: 381 MW
Total requested
381 MW
Service type
NRIS and ERIS
Study phase
Facility Study
Queue status
Active
Entered queue
25 May 2018
Proposed online date
December 2023

Location

Marker shows the centre of Klickitat County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Klickitat County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem