🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Washington

SOLAR + STORAGE · WEST

Solar + storage project G0844, Klickitat County

Solar + storage project G0844, Klickitat County is a 420 MW solar + storage request in interconnection study in the West interconnection queue, in Klickitat County, Washington.

Queue statusIn planning
  1. PlanningQueued Feb 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G0844
Grid region
West (non-ISO utilities)
Connection point (POI)
Horse Heaven-Harvalum No 1 230kV line.
Location
Klickitat County, Washington
Technology
Solar: 280 MW · Battery: 140 MW
Total requested
420 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
22 February 2023
Proposed online date
June 2026

Location

Marker shows the centre of Klickitat County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Klickitat County