Big Field Solar

Big Field Solar is a 506 MW solar request in interconnection study in the ERCOT interconnection queue, in Wilbarger County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
29INR0148
Grid region
ERCOT (Texas)
Developer
Big Field Solar Energy LLC
Connection point (POI)
6101 RILEY7A 345kV
Location
Wilbarger County, Texas
Technology
Solar: 506 MW
Total requested
506 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
11 June 2025
Proposed online date
December 2029

Location

Marker shows the centre of Wilbarger County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Wilbarger County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem