United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Felix North Solar

Felix North Solar is a 201 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Wilbarger County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2019 (completed)
  2. ConsentedFeb 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0209
Grid region
ERCOT (Texas)
Developer
Crescent Solar, LLC
Connection point (POI)
6101 Riley 345kV
Location
Wilbarger County, Texas
Technology
Solar: 201 MW · Battery
Total requested
201 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
17 January 2019
Agreement signed
21 February 2025
Proposed online date
December 2028

Location

Marker shows the centre of Wilbarger County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Wilbarger County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem