πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

GAS Β· ERCOT

Texpo

Texpo is a 680 MW gas request in interconnection study in the ERCOT interconnection queue, in Wilbarger County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
22INR0497
Grid region
ERCOT (Texas)
Developer
Oklaunion Power Station, LLC
Connection point (POI)
6100 Oklaunion 345kV
Location
Wilbarger County, Texas
Technology
Gas: 680 MW
Total requested
680 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
16 March 2021
Proposed online date
October 2027

Location

Marker shows the centre of Wilbarger County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Wilbarger County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem