🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

Blackwater Solar

Blackwater Solar is a 800 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Sussex County, Virginia, connecting to Dominion.

Queue statusConsented
  1. PlanningQueued Sep 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AE1-173
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Carson-Suffolk 500 kV
Location
Sussex County, Virginia
Technology
Solar: 800 MW
Total requested
800 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
25 September 2018
Proposed online date
October 2029

Location

Marker shows the centre of Sussex County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Sussex County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem