SOLAR + STORAGE · PJM

Cassius Blue Solar

Cassius Blue Solar is a 300 MW solar + storage request with a signed interconnection agreement in the PJM interconnection queue, in Sussex County, Virginia, connecting to Dominion.

Queue statusConsented
  1. PlanningQueued Feb 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2031 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AE2-094
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Carson-Rogers Road 500 kV
Location
Sussex County, Virginia
Technology
Solar: 300 MW · Battery
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
26 February 2019
Proposed online date
August 2031

Location

Marker shows the centre of Sussex County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia