Solar project G0673, Crook County

Solar project G0673, Crook County is a 600 MW solar request in interconnection study in the West interconnection queue, in Crook County, Oregon.

Queue statusIn planning
  1. PlanningQueued Mar 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G0673
Grid region
West (non-ISO utilities)
Connection point (POI)
Ponderosa 500 kV
Location
Crook County, Oregon
Technology
Solar: 600 MW
Total requested
600 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
9 March 2021
Proposed online date
April 2028

Location

Marker shows the centre of Crook County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Crook County