Solar + storage project 731, Crook County

Solar + storage project 731, Crook County is a 55.0 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Crook County, Oregon, connecting to PacifiCorp.

Queue statusConsented
  1. PlanningQueued Mar 2016 (completed)
  2. ConsentedNov 2018 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
731
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Prineville Solar Energy LLC
Connection point (POI)
Baldwin Rd Ponderosa transmission line
Location
Crook County, Oregon
Technology
Solar: 55.0 MW · Battery
Total requested
55.0 MW
Service type
Energy only (ERIS)
Study phase
IA executed 11/5/18
Queue status
Active
Entered queue
4 March 2016
Agreement signed
5 November 2018
Proposed online date
August 2025

Location

Marker shows the centre of Crook County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Crook County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem