United States › Grid › Interconnection queues › Oregon
SOLAR + STORAGE · WESTSolar + storage project TCS-54, Crook County
Solar + storage project TCS-54, Crook County is a 40.0 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Crook County, Oregon, connecting to PacifiCorp.
Queue statusConsented
- PlanningQueued Apr 2020 (completed)
- ConsentedOct 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Oct 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- TCS-54
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- SSEV C LLC
- Connection point (POI)
- Ponderosa substation
- Location
- Crook County, Oregon
- Technology
- Solar: 40.0 MW · Battery
- Total requested
- 40.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- OLGIA executed 10/10/2023
- Queue status
- Active
- Entered queue
- 13 April 2020
- Agreement signed
- 10 October 2023
- Proposed online date
- October 2026
Location
Marker shows the centre of Crook County; the queue data does not give exact sites.
Other requests in Crook County
- Solar + storage project C2-158, Crook CountySolar + storage · 199 MW · agreement signed
- Solar + storage project C2-114, Crook CountySolar + storage · 199 MW · agreement signed
- Battery storage project C2-178, Crook CountyBattery storage · 199 MW · agreement signed
- Solar project 734, Crook CountySolar · 102 MW · agreement signed
- Solar + storage project TCS-44, Crook CountySolar + storage · 80.0 MW · agreement signed
- Solar + storage project C2-07, Crook CountySolar + storage · 80.0 MW · agreement signed
- Solar project C2-06, Crook CountySolar · 80.0 MW · agreement signed
- Solar + storage project C2-08, Crook CountySolar + storage · 80.0 MW · agreement signed
- Solar + storage project C2-09, Crook CountySolar + storage · 80.0 MW · agreement signed
- Solar + storage project 731, Crook CountySolar + storage · 55.0 MW · agreement signed
- Solar + storage project TCS-45, Crook CountySolar + storage · 40.0 MW · agreement signed
- Solar + storage project TCS-43, Crook CountySolar + storage · 40.0 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem