United States › Grid › Interconnection queues › Colorado
ONSHORE WIND · WESTOnshore wind project GI-2016-14, Cheyenne County
Onshore wind project GI-2016-14, Cheyenne County is a 500 MW onshore wind request with a signed interconnection agreement in the West interconnection queue, in Cheyenne County, Colorado, connecting to Public Service Company Of Colorado.
Queue statusConsented
- PlanningQueued Jul 2016 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingAug 2020 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GI-2016-14
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company Of Colorado
- Connection point (POI)
- Missile Site Substation 345kV
- Location
- Cheyenne County, Colorado
- Technology
- Wind: 500 MW
- Total requested
- 500 MW
- Service type
- Energy only (ERIS)
- Study phase
- Feasibility Study Complete System Impact Study Complete Facility Study Complete LGIA Signed
- Queue status
- Active
- Entered queue
- 11 July 2016
- Proposed online date
- December 2018
- Came online
- August 2020
Location
Marker shows the centre of Cheyenne County; the queue data does not give exact sites.
Other requests in Cheyenne County
- Onshore wind project 5RSC-2024-16, Cheyenne CountyOnshore wind · 450 MW · in study
- Solar project GI-2025-09, Cheyenne CountySolar · 400 MW · in study
- Solar + storage project GI-2025-02, Cheyenne CountySolar + storage · 300 MW · in study
- Battery storage project 5RSC-2024-10, Cheyenne CountyBattery storage · 250 MW · in study
- Solar project GI-TC-2024-07, Cheyenne CountySolar · 199 MW · in study
- Onshore wind project GI-2020-14, Cheyenne CountyOnshore wind · 700 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem