🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Colorado

SOLAR · WEST

Solar project GI-2025-09, Cheyenne County

Solar project GI-2025-09, Cheyenne County is a 400 MW solar request in interconnection study in the West interconnection queue, in Cheyenne County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-2025-09
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Shortgrass-Goose Creek 345 kV line
Location
Cheyenne County, Colorado
Technology
Solar: 400 MW
Total requested
400 MW
Service type
Network resource (NRIS)
Study phase
Detailed status: Study to be started after completion of 2024 DISIS
Queue status
Active
Entered queue
25 April 2025
Proposed online date
December 2029

Location

Marker shows the centre of Cheyenne County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Cheyenne County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem