🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Montana

ONSHORE WIND · WEST

Onshore wind project 357, Rosebud County

Onshore wind project 357, Rosebud County is a 750 MW onshore wind request in interconnection study in the West interconnection queue, in Rosebud County, Montana, connecting to NorthWestern Energy.

Queue statusIn planning
  1. PlanningQueued Oct 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2021 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
357
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
500kV at Colstrip Substation
Location
Rosebud County, Montana
Technology
Wind: 750 MW
Total requested
750 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study System Impact Study Facilities Study
Queue status
Active
Entered queue
9 October 2018
Proposed online date
September 2021

Location

Marker shows the centre of Rosebud County; the queue data does not give exact sites.

Power plants in Montana · Transmission lines in Montana

Other requests in Rosebud County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem