United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTBuffalo Jump Wind
Buffalo Jump Wind is a 740 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Culberson County, Texas.
Queue statusIn planning
- PlanningQueued Nov 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0334
- Grid region
- ERCOT (Texas)
- Developer
- BOULEVARD ASSOCIATES, LLC
- Connection point (POI)
- 1097 Culberson 345 KV
- Location
- Culberson County, Texas
- Technology
- Wind: 740 MW
- Total requested
- 740 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 5 November 2025
- Proposed online date
- July 2029
Location
Marker shows the centre of Culberson County; the queue data does not give exact sites.
Other requests in Culberson County
- Delaware Ranch SolarSolar · 36.0 MW · agreement signed
- Hayhurst Texas SolarSolar · 24.8 MW · agreement signed
- Salt-Lick SolarSolar + storage · 453 MW · in study
- Salt-Lick StorageSolar + storage · 155 MW · in study
- Titan SolarSolar · 270 MW · built
- Aragorn SolarSolar · 187 MW · built
- Screwbean BESSOther · 10.0 MW · built
- Gusty Hill WindOnshore wind · 350 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem