United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTDelaware Ranch Solar
Delaware Ranch Solar is a 36.0 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Culberson County, Texas.
Queue statusConsented
- PlanningQueued Dec 2020 (completed)
- ConsentedFeb 2022 (current stage)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 22INR0454
- Grid region
- ERCOT (Texas)
- Developer
- Delaware Ranch Solar, LLC
- Connection point (POI)
- Delaware River SW (11112)
- Location
- Culberson County, Texas
- Technology
- Solar: 36.0 MW
- Total requested
- 36.0 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 22 December 2020
- Agreement signed
- 7 February 2022
- Proposed online date
- September 2026
Location
Marker shows the centre of Culberson County; the queue data does not give exact sites.
Other requests in Culberson County
- Hayhurst Texas SolarSolar · 24.8 MW · agreement signed
- Buffalo Jump WindOnshore wind · 740 MW · in study
- Salt-Lick SolarSolar + storage · 453 MW · in study
- Salt-Lick StorageSolar + storage · 155 MW · in study
- Titan SolarSolar · 270 MW · built
- Aragorn SolarSolar · 187 MW · built
- Screwbean BESSOther · 10.0 MW · built
- Gusty Hill WindOnshore wind · 350 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem