United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTSalt-Lick Storage
Salt-Lick Storage is a 155 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Culberson County, Texas.
Queue statusIn planning
- PlanningQueued Oct 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 28INR0134
- Grid region
- ERCOT (Texas)
- Developer
- Salt-Lick Storage, LLC
- Connection point (POI)
- 11198 Elcor_8 138 KV
- Location
- Culberson County, Texas
- Technology
- Battery: 155 MW · Battery
- Total requested
- 155 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 10 October 2024
- Proposed online date
- June 2028
Location
Marker shows the centre of Culberson County; the queue data does not give exact sites.
Other requests in Culberson County
- Delaware Ranch SolarSolar · 36.0 MW · agreement signed
- Hayhurst Texas SolarSolar · 24.8 MW · agreement signed
- Buffalo Jump WindOnshore wind · 740 MW · in study
- Salt-Lick SolarSolar + storage · 453 MW · in study
- Titan SolarSolar · 270 MW · built
- Aragorn SolarSolar · 187 MW · built
- Screwbean BESSOther · 10.0 MW · built
- Gusty Hill WindOnshore wind · 350 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem