ONSHORE WIND Β· ERCOT

Gusty Hill Wind

Gusty Hill Wind is a 350 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Culberson County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2018 (completed)
  2. Withdrawn / abandonedNov 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0116
Grid region
ERCOT (Texas)
Developer
Gusty Hill Wind Project, LLC
Connection point (POI)
tap 138kV 7387 Kunitz - 71097 Culberson
Location
Culberson County, Texas
Technology
Wind: 350 MW
Total requested
350 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
28 June 2018
Proposed online date
December 2022
Withdrawn
November 2019

Location

Marker shows the centre of Culberson County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Culberson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem