Aurelius Wind

Aurelius Wind is a 622 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Deaf Smith County, Texas.

Queue statusConsented
  1. PlanningQueued Aug 2023 (completed)
  2. ConsentedOct 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
29INR0004
Grid region
ERCOT (Texas)
Developer
IP Roman Wind, LLC
Connection point (POI)
23908 Deaf Smith station 345 kV
Location
Deaf Smith County, Texas
Technology
Wind: 622 MW
Total requested
622 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
14 August 2023
Agreement signed
9 October 2025
Proposed online date
June 2028

Location

Marker shows the centre of Deaf Smith County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Deaf Smith County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem