United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTBRP Hemera BESS
BRP Hemera BESS is a 207 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Deaf Smith County, Texas.
Queue statusIn planning
- PlanningQueued Dec 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 24INR0134
- Grid region
- ERCOT (Texas)
- Developer
- BRP Hemera BESS LLC
- Connection point (POI)
- 345 kV Deaf Smith Substation (#23908, Oncor)
- Location
- Deaf Smith County, Texas
- Technology
- Battery: 207 MW
- Total requested
- 207 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 29 December 2021
- Proposed online date
- December 2029
Location
Marker shows the centre of Deaf Smith County; the queue data does not give exact sites.
Other requests in Deaf Smith County
- Aurelius SolarSolar · 1,124 MW · agreement signed
- Aurelius WindOnshore wind · 622 MW · agreement signed
- Renegade ProjectSolar · 516 MW · agreement signed
- Caliche Mound SolarSolar · 407 MW · agreement signed
- Aurelius 3 WindOnshore wind · 623 MW · in study
- Aurelius 2 WindOnshore wind · 622 MW · in study
- Aurelius 2 SolarSolar · 445 MW · in study
- Aurelius 3 SolarSolar · 445 MW · in study
- White Tail SolarSolar · 227 MW · in study
- Gas project GEN-2014-067, Deaf Smith CountyGas · 356 MW · withdrawn
- Frio Flat WindOnshore wind · 305 MW · withdrawn
- Solar project GEN-2024-363, Deaf Smith CountySolar · 300 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem