Gas project GEN-2014-067, Deaf Smith County

Gas project GEN-2014-067, Deaf Smith County is a 356 MW gas request withdrawn in the SPP interconnection queue, in Deaf Smith County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2014 (completed)
  2. Withdrawn / abandonedFeb 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2014-067
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tap Potter County - New Hart 230kV
Location
Deaf Smith County, Texas
Technology
Gas: 356 MW
Total requested
356 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 September 2014
Proposed online date
March 2019
Withdrawn
February 2015

Location

Marker shows the centre of Deaf Smith County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Deaf Smith County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem