🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

White Tail Solar

White Tail Solar is a 227 MW solar request in interconnection study in the ERCOT interconnection queue, in Deaf Smith County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0200
Grid region
ERCOT (Texas)
Developer
Mule Deer Solar LLC
Connection point (POI)
Tap 345kV Windmill (23910) – AJ Swope (23906)
Location
Deaf Smith County, Texas
Technology
Solar: 227 MW
Total requested
227 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
7 February 2022
Proposed online date
September 2027

Location

Marker shows the centre of Deaf Smith County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Deaf Smith County