United States › Grid › Interconnection queues › Minnesota

SOLAR · MISO

Solar project J2885, Red Lake County

Solar project J2885, Red Lake County is a 130 MW solar request in interconnection study in the MISO interconnection queue, in Red Lake County, Minnesota, connecting to OTTER TAIL POWER COMPANY.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2885
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Plummer Pipe
Location
Red Lake County, Minnesota
Technology
Solar: 130 MW
Total requested
130 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
6 September 2022
Proposed online date
January 2025

Location

Marker shows the centre of Red Lake County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Red Lake County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem