United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTPecan Prairie South
Pecan Prairie South is a 131 MW solar request in interconnection study in the ERCOT interconnection queue, in Leon County, Texas.
Queue statusIn planning
- PlanningQueued Aug 2019 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 21INR0371
- Grid region
- ERCOT (Texas)
- Developer
- ConnectGen Operating LLC
- Connection point (POI)
- CTT Yellow Wolf, bus # 79007
- Location
- Leon County, Texas
- Technology
- Solar: 131 MW
- Total requested
- 131 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 16 August 2019
- Proposed online date
- May 2027
Location
Marker shows the centre of Leon County; the queue data does not give exact sites.
Other requests in Leon County
- Hollow Branch Creek SolarSolar + storage · 460 MW · agreement signed
- Pecan Prairie NorthSolar · 321 MW · agreement signed
- Great Rock BESSBattery storage · 301 MW · agreement signed
- Leon Solar ParkSolar + storage · 210 MW · agreement signed
- Hollow Branch Creek StorageSolar + storage · 460 MW · in study
- Dempsey Solar SLFSolar + storage · 245 MW · in study
- Kahla StorageBattery storage · 201 MW · in study
- Pecan BESSBattery storage · 157 MW · in study
- Nickel Spruce SolarSolar · 150 MW · in study
- HIP ESS ProjectOther · 60.0 MW · suspended
- Hollow Branch Creek Solar SLFSolar · 712 MW · withdrawn
- Lazy J SolarSolar · 300 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem