Leon Solar Park

Leon Solar Park is a 210 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Leon County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2022 (completed)
  2. ConsentedMay 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
26INR0023
Grid region
ERCOT (Texas)
Developer
Misae Solar IV LLC
Connection point (POI)
Tap 138kV Grapeland Magnolia Tap (bus #3355) to Pleasant Springs POI (bus# 3357) section of the Jewett -Crockett 138kV Line
Location
Leon County, Texas
Technology
Solar: 210 MW · Battery
Total requested
210 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
15 September 2022
Agreement signed
21 May 2024
Proposed online date
July 2026

Location

Marker shows the centre of Leon County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Leon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem