United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTHollow Branch Creek Solar
Hollow Branch Creek Solar is a 460 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Leon County, Texas.
Queue statusConsented
- PlanningQueued Sep 2022 (completed)
- ConsentedOct 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 24INR0422
- Grid region
- ERCOT (Texas)
- Developer
- Hollow Branch Creek Solar LLC
- Connection point (POI)
- Tap 345kV 3390 Jewett - 44645 Singleton
- Location
- Leon County, Texas
- Technology
- Solar: 460 MW · Battery
- Total requested
- 460 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 2 September 2022
- Agreement signed
- 22 October 2024
- Proposed online date
- December 2027
Location
Marker shows the centre of Leon County; the queue data does not give exact sites.
Other requests in Leon County
- Pecan Prairie NorthSolar · 321 MW · agreement signed
- Great Rock BESSBattery storage · 301 MW · agreement signed
- Leon Solar ParkSolar + storage · 210 MW · agreement signed
- Hollow Branch Creek StorageSolar + storage · 460 MW · in study
- Dempsey Solar SLFSolar + storage · 245 MW · in study
- Kahla StorageBattery storage · 201 MW · in study
- Pecan BESSBattery storage · 157 MW · in study
- Nickel Spruce SolarSolar · 150 MW · in study
- Pecan Prairie SouthSolar · 131 MW · in study
- HIP ESS ProjectOther · 60.0 MW · suspended
- Hollow Branch Creek Solar SLFSolar · 712 MW · withdrawn
- Lazy J SolarSolar · 300 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem