United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Pecan Prairie North

Pecan Prairie North is a 321 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Leon County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2019 (completed)
  2. ConsentedFeb 2021 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0428
Grid region
ERCOT (Texas)
Developer
CG Leon County II LLC
Connection point (POI)
CTT Yellow Wolf, bus # 79007
Location
Leon County, Texas
Technology
Solar: 321 MW
Total requested
321 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
23 September 2019
Agreement signed
26 February 2021
Proposed online date
May 2027

Location

Marker shows the centre of Leon County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Leon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem