United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTMillers Branch Solar III
Millers Branch Solar III is a 133 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Haskell County, Texas.
Queue statusConsented
- PlanningQueued Aug 2024 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Aug 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 26INR0521
- Grid region
- ERCOT (Texas)
- Developer
- Miller's Branch Solar LLC
- Connection point (POI)
- Tap 345kV 60703 Gauss - 60514 Clear Crossing (60712 QUASAR)
- Location
- Haskell County, Texas
- Technology
- Solar: 133 MW
- Total requested
- 133 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 16 August 2024
- Proposed online date
- August 2026
Location
Marker shows the centre of Haskell County; the queue data does not give exact sites.
Other requests in Haskell County
- Briggs StorageSolar + storage · 336 MW · agreement signed
- Briggs SolarSolar + storage · 324 MW · agreement signed
- Quantum StorageSolar + storage · 322 MW · agreement signed
- Solace StorageSolar + storage · 322 MW · agreement signed
- Quantum SolarSolar + storage · 322 MW · agreement signed
- Solace SolarSolar + storage · 322 MW · agreement signed
- Rubicon Alpha WindOnshore wind · 226 MW · agreement signed
- Inertia SolarSolar · 202 MW · agreement signed
- Millers Branch Solar ISolar · 200 MW · agreement signed
- Millers Branch Solar IISolar · 178 MW · agreement signed
- Grasshopper SolarSolar · 408 MW · in study
- Scott Crossing Solar SLFSolar + storage · 364 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem