🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Grasshopper Solar

Grasshopper Solar is a 408 MW solar request in interconnection study in the ERCOT interconnection queue, in Haskell County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0125
Grid region
ERCOT (Texas)
Developer
Grasshopper Solar LLC
Connection point (POI)
Smoky Hill 345kV Sub (Bus #6104) Locational coordinates : 33.34414; 99.624637
Location
Haskell County, Texas
Technology
Solar: 408 MW
Total requested
408 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
28 September 2021
Proposed online date
October 2028

Location

Marker shows the centre of Haskell County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Haskell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem