🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Millers Branch Solar I

Millers Branch Solar I is a 200 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Haskell County, Texas.

Queue statusConsented
  1. PlanningQueued Dec 2019 (completed)
  2. ConsentedJun 2021 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0270
Grid region
ERCOT (Texas)
Developer
Miller's Branch Solar, LLC
Connection point (POI)
Tap 345kV 60703 Gauss - 60514 Clear Crossing (60712 QUASAR)
Location
Haskell County, Texas
Technology
Solar: 200 MW
Total requested
200 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
17 December 2019
Agreement signed
14 June 2021
Proposed online date
December 2025

Location

Marker shows the centre of Haskell County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Haskell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem