SOLAR · MISOSolar project J2809, Iroquois County
Solar project J2809, Iroquois County is a 133 MW solar request in interconnection study in the MISO interconnection queue, in Iroquois County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2809
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- 4GILMAN - 4PAXTON E 138 kV
- Location
- Iroquois County, Illinois
- Technology
- Solar: 133 MW
- Total requested
- 133 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 14 September 2022
- Proposed online date
- September 2026
Location
Marker shows the centre of Iroquois County; the queue data does not give exact sites.
Other requests in Iroquois County
- Wind + storage project J3015, Iroquois CountyWind + storage · 400 MW · in study
- Onshore wind project J3853, Iroquois CountyOnshore wind · 300 MW · in study
- Solar project J2565, Iroquois CountySolar · 265 MW · in study
- Onshore wind project J3753, Iroquois CountyOnshore wind · 196 MW · in study
- Solar project J2136, Iroquois CountySolar · 191 MW · in study
- Onshore wind project J3754, Iroquois CountyOnshore wind · 147 MW · in study
- Onshore wind project J3755, Iroquois CountyOnshore wind · 147 MW · in study
- Onshore wind project G931, Iroquois CountyOnshore wind · 150 MW · built
- Onshore wind project U2-065, Iroquois CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project T120, Iroquois CountyOnshore wind · 250 MW · withdrawn
- Solar project J3867, Iroquois CountySolar · 200 MW · withdrawn
- Onshore wind project J277, Iroquois CountyOnshore wind · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem