United States › Grid › Interconnection queues › Illinois
ONSHORE WIND · MISOOnshore wind project G931, Iroquois County
Onshore wind project G931, Iroquois County is a 150 MW onshore wind request built and operating in the MISO interconnection queue, in Iroquois County, Illinois.
Request details
- Queue ID
- G931
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Watseka - Goodland 138kV
- Location
- Iroquois County, Illinois
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- Optional
- Queue status
- Operational
- Entered queue
- 11 December 2007
- Agreement signed
- 8 February 2010
- Proposed online date
- March 2009
- Came online
- March 2009
Location
Marker shows the centre of Iroquois County; the queue data does not give exact sites.
Other requests in Iroquois County
- Wind + storage project J3015, Iroquois CountyWind + storage · 400 MW · in study
- Onshore wind project J3853, Iroquois CountyOnshore wind · 300 MW · in study
- Solar project J2565, Iroquois CountySolar · 265 MW · in study
- Onshore wind project J3753, Iroquois CountyOnshore wind · 196 MW · in study
- Solar project J2136, Iroquois CountySolar · 191 MW · in study
- Onshore wind project J3754, Iroquois CountyOnshore wind · 147 MW · in study
- Onshore wind project J3755, Iroquois CountyOnshore wind · 147 MW · in study
- Solar project J2809, Iroquois CountySolar · 133 MW · in study
- Onshore wind project U2-065, Iroquois CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project T120, Iroquois CountyOnshore wind · 250 MW · withdrawn
- Solar project J3867, Iroquois CountySolar · 200 MW · withdrawn
- Onshore wind project J277, Iroquois CountyOnshore wind · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem