πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

SOLAR Β· MISO

Solar project J3867, Iroquois County

Solar project J3867, Iroquois County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Iroquois County, Illinois, connecting to AMEREN TRANSMISSION COMPANY OF ILLINOIS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2024 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3867
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Connection point (POI)
Watseka
Location
Iroquois County, Illinois
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
2 December 2024
Proposed online date
June 2029
Withdrawn
December 2025

Location

Marker shows the centre of Iroquois County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Iroquois County