Interconnection queue in the USA — page 57

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 57 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Mesquite Creek Windpower Repower
Onshore wind · Mesquite Creek Wind LLC
213 MWIn study Dawson, TXERCOT Apr 2025target 2027
Replacing 30 MW of existing coal generation with BESS at Burlington Generation Station; Burlington 5
Other
212 MWIn study Des Moines, IAMISO Feb 2022target 2024
BumbleBee Solar
Solar · BumbleBee Solar Farm LLC
212 MWIn study Bee, TXERCOT Feb 2024target 2027
Rock Rose BESS
Battery storage · Rock Rose Energy Storage LLC
212 MWAgreement signed Fort Bend, TXERCOT Sep 2023target 2026
Vazlon Solar SLF
Solar + storage · Vazlon Energy LLC
211 MWIn study La Salle, TXERCOT Oct 2024target 2028
Grimes County Solar
Solar · Grimes County Solar Project, LLC
211 MWAgreement signed Grimes, TXERCOT Jan 2021target 2025
Rockridge Solar
Solar · Magnolia Solar Development LLC
211 MWAgreement signed Guadalupe, TXERCOT Apr 2022target 2027
Gypsum Plains Storage
Solar + storage · Gypsum Plains Solar, LLC
211 MWIn study Ector, TXERCOT Jan 2025target 2029
Gas project J3465, Isanti County
Gas
211 MWIn study Isanti, MNMISO Mar 2024target 2026
Bessie Storage
Battery storage · Bessie Energy Storage, LLC
211 MWIn study Starr, TXERCOT Feb 2022target 2026
Cumulus Grid BESS
Battery storage · Cumulus Grid, LLC
211 MWAgreement signed Ellis, TXERCOT Mar 2022target 2028
Val Vista Grid BESS 2
Battery storage · Val Vista Grid, LLC
211 MWIn study Hidalgo, TXERCOT Oct 2021target 2028
Guadalupe Battery Storage Project
Battery storage · Guadalupe Power Partners, LP
211 MWIn study Guadalupe, TXERCOT Nov 2023target 2027
Freestone Battery Storage Project
Battery storage · Freestone Power Generation, LLC
211 MWIn study Freestone, TXERCOT Feb 2024target 2028
Leon Solar Park
Solar + storage · Misae Solar IV LLC
210 MWAgreement signed Leon, TXERCOT Sep 2022target 2026
Solar project J2811, Cerro Gordo County
Solar
210 MWIn study Cerro Gordo, IAMISO Sep 2022target 2026
Hydro project G0535, Walla Walla County
Hydro
210 MWIn study Walla Walla, WAWest May 2016target 2031
Battery storage project S0027, Walla Walla County
Battery storage
210 MWIn study Walla Walla, WAWest Feb 2024target 2026
Solar project AG2-245, Starke County
Solar · STARKE CENTRAL PROJECT, LLC
210 MWIn study Starke, INPJM Mar 2025target 2023
Battery storage project AI1-185, Augusta County
Battery storage
210 MWIn study Augusta, VAPJM Sep 2022target 2027
Solar project AG2-184, Knott County
Solar · STMO bn, LLC
210 MWIn study Knott, KYPJM Feb 2025target 2024
Elk Unit 4
Gas · Golden Spread Electric Cooperative, Inc.
210 MWIn study Hale, TXERCOT Apr 2024target 2027
Solar project J2553, Cerro Gordo County
Solar
210 MWIn study Cerro Gordo, IAMISO Sep 2022target 2026
Solar + storage project AH2-419, Laporte County
Solar + storage
210 MWIn study Laporte, INPJM Mar 2022target 2026
Broomstick Solar Energy Centergy Center
Solar
210 MWPaused / redesign Christian, ILPJM Mar 2018target 2028
Other project IA-PNM-2023-10, Mckinley County
Other
210 MWIn study Mckinley, NMWest Jan 2023target 2028
Alamosa Solar
Solar
210 MWPaused / redesign Wilbarger, TXERCOT Dec 2020target 2025
Val Vista Grid BESS 1
Battery storage · Val Vista Grid, LLC
209 MWIn study Hidalgo, TXERCOT Aug 2020target 2028
New Hickory Solar
Solar · New Hickory Solar LLC
209 MWAgreement signed Jackson, TXERCOT Jan 2019target 2026
Moonlit Bayou Storage
Battery storage · Moonlit Bayou Energy Center, LLC
209 MWIn study Fayette, TXERCOT Feb 2024target 2028
Treehouse Storage
Solar + storage · Treehouse Solar, LLC
209 MWIn study Grimes, TXERCOT Jul 2025target 2028
Battery storage project GEN-2025-SR30, Dewey County
Battery storage
209 MWIn study Dewey, OKSPP Aug 2025target 2027
Anila BESS
Solar + storage · Alina Energy LLC
209 MWAgreement signed Wilson, TXERCOT Feb 2023target 2028
Gas project 200, Anderson County
Gas
209 MWIn study Anderson, SCSoutheast Jun 2023
Hornet Solar II SLF
Solar + storage · Hornet Solar II LLC
209 MWAgreement signed Swisher, TXERCOT Jan 2023target 2028
Clapton Storage
Solar + storage · Clapton BESS
209 MWIn study Mills, TXERCOT Mar 2024target 2028
Sorghum BESS
Battery storage · Blue Creek BESS, LLC
209 MWAgreement signed Wharton, TXERCOT Apr 2024target 2027
Sisters Storage
Solar + storage · 174 Power Global Properties
209 MWIn study Ector, TXERCOT Dec 2019target 2027
Starlit Pasture Storage
Battery storage · Starlit Pasture Energy Center, LLC
209 MWIn study Washington, TXERCOT Aug 2024target 2029
Revolution BESS
Battery storage · Nova Clean Energy LLC
209 MWIn study La Salle, TXERCOT May 2024target 2027
Zeus Rusk BESS
Solar + storage · Rusk BESS, LLC
209 MWIn study Rusk, TXERCOT Apr 2024target 2027
Forts Trail BESS
Solar + storage · JC Central Bluff, LLC
209 MWIn study Taylor, TXERCOT Jun 2022target 2028
Two Rivers Solar
Solar · Two Rivers Solar, LLC
209 MWIn study Milam, TXERCOT Jul 2021target 2029
Battery storage project MPC04600, Eddy County
Battery storage
209 MWIn study Eddy, NDMISO Nov 2025target 2028
Alwest BESS
Battery storage · Castleman Power
209 MWIn study Anderson, TXERCOT Aug 2021target 2028
Jolly Rock Storage Center
Battery storage · Jolly Rock Storage Center LLC
209 MWIn study Young, TXERCOT Dec 2024target 2029
Gusty Windpower
Onshore wind · Gusty Windpower, LLC
209 MWAgreement signed Glasscock, TXERCOT Jul 2024target 2028
Pearl Crescent Solar
Solar + storage · RWE Solar Development, LLC
208 MWIn study Colorado, TXERCOT May 2019target 2026
Solar project J2050, Macon County
Solar
208 MWIn study Macon, MOMISO Mar 2022target 2024
New Minglewood Energy Center
Battery storage · Nova Clean Energy LLC
208 MWIn study Ward, TXERCOT May 2024target 2027
Page 57 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)