BATTERY STORAGE · PJM

Battery storage project AI1-185, Augusta County

Battery storage project AI1-185, Augusta County is a 210 MW battery storage request in interconnection study in the PJM interconnection queue, in Augusta County, Virginia, connecting to Dominion.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AI1-185
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Valley 230 kV
Location
Augusta County, Virginia
Technology
Battery: 210 MW
Total requested
210 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
9 September 2022
Proposed online date
December 2027

Location

Marker shows the centre of Augusta County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Augusta County