Solar project AI2-036, Augusta County

Solar project AI2-036, Augusta County is a 100 MW solar request in interconnection study in the PJM interconnection queue, in Augusta County, Virginia, connecting to Dominion.

Queue statusIn planning
  1. PlanningQueued Jan 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AI2-036
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Craigsville-Staunton 115kV
Location
Augusta County, Virginia
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
25 January 2023
Proposed online date
December 2027

Location

Marker shows the centre of Augusta County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Augusta County