SOLAR + STORAGE · ERCOT

Treehouse Storage

Treehouse Storage is a 209 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Grimes County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0395
Grid region
ERCOT (Texas)
Developer
Treehouse Solar, LLC
Connection point (POI)
Tap the 345 kV Jewett (#3390) - Singleton (#44645) line, ONCOR
Location
Grimes County, Texas
Technology
Battery: 209 MW · Battery
Total requested
209 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
29 July 2025
Proposed online date
November 2028

Location

Marker shows the centre of Grimes County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Grimes County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem