BATTERY STORAGE · ERCOT

BRP Artemis BESS

BRP Artemis BESS is a 411 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Grimes County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0130
Grid region
ERCOT (Texas)
Developer
BRP Artemis BESS LLC
Connection point (POI)
40600 Roans Prairie Substation 345kV
Location
Grimes County, Texas
Technology
Battery: 411 MW
Total requested
411 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
20 December 2021
Proposed online date
December 2028

Location

Marker shows the centre of Grimes County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Grimes County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem