BATTERY STORAGE · ERCOT

Diamante BESS

Diamante BESS is a 514 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Grimes County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0115
Grid region
ERCOT (Texas)
Developer
Flexen USA LLC
Connection point (POI)
40600 ROANS__POI_5 345kV
Location
Grimes County, Texas
Technology
Battery: 514 MW
Total requested
514 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
27 February 2024
Proposed online date
November 2028

Location

Marker shows the centre of Grimes County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Grimes County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem