United States › Grid › Interconnection queues › Missouri

SOLAR · MISO

Solar project J2050, Macon County

Solar project J2050, Macon County is a 208 MW solar request in interconnection study in the MISO interconnection queue, in Macon County, Missouri, connecting to AMEREN MISSOURI.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2050
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN MISSOURI
Connection point (POI)
Thomas Hill-Adair-1 161kV
Location
Macon County, Missouri
Technology
Solar: 208 MW
Total requested
208 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
28 March 2022
Proposed online date
October 2024

Location

Marker shows the centre of Macon County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri

Other requests in Macon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem