United States › Grid › Interconnection queues › North Dakota
BATTERY STORAGE · MISOBattery storage project MPC04600, Eddy County
Battery storage project MPC04600, Eddy County is a 209 MW battery storage request in interconnection study in the MISO interconnection queue, in Eddy County, North Dakota, connecting to Minnkota Power Cooperative.
- PlanningQueued Nov 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- MPC04600
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Minnkota Power Cooperative
- Connection point (POI)
- Center-Prairie 345 kV Line
- Location
- Eddy County, North Dakota
- Technology
- Battery: 209 MW
- Total requested
- 209 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 25 November 2025
- Proposed online date
- December 2028
Location
Marker shows the centre of Eddy County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Eddy County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem