United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Hornet Solar II SLF

Hornet Solar II SLF is a 209 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Swisher County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2023 (completed)
  2. ConsentedAug 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0282
Grid region
ERCOT (Texas)
Developer
Hornet Solar II LLC
Connection point (POI)
Ozark Trail Switch 345kV substation (Bus #23901)
Location
Swisher County, Texas
Technology
Solar: 209 MW · Battery
Total requested
209 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
3 January 2023
Agreement signed
21 August 2024
Proposed online date
March 2028

Location

Marker shows the centre of Swisher County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Swisher County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem