United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTHornet Solar
Hornet Solar is a 602 MW solar request built and operating in the ERCOT interconnection queue, in Swisher County, Texas.
Request details
- Queue ID
- 23INR0021
- Grid region
- ERCOT (Texas)
- Developer
- Hornet Solar LLC
- Connection point (POI)
- tap 345kV 23914 Tule Canyon - 23912 Ogallala
- Location
- Swisher County, Texas
- Technology
- Solar: 602 MW
- Total requested
- 602 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 3 February 2020
- Agreement signed
- 6 December 2021
- Proposed online date
- October 2025
- Came online
- August 2024
Location
Marker shows the centre of Swisher County; the queue data does not give exact sites.
Other requests in Swisher County
- Hornet Solar II SLFSolar + storage Β· 209 MW Β· agreement signed
- Commodus 2 WindOnshore wind Β· 642 MW Β· in study
- Frye StorageSolar + storage Β· 504 MW Β· in study
- Commodus 2 SolarSolar Β· 502 MW Β· in study
- Stem SolarSolar Β· 200 MW Β· in study
- Solar project GEN-2023-120, Swisher CountySolar Β· 130 MW Β· in study
- Frye SolarSolar + storage Β· 502 MW Β· built
- Comanche Run WindOnshore wind Β· 500 MW Β· withdrawn
- Battery storage project GEN-2019-064, Swisher CountyBattery storage Β· 400 MW Β· withdrawn
- Wildrose WindOnshore wind Β· 303 MW Β· withdrawn
- Lazarus SolarSolar Β· 300 MW Β· withdrawn
- Onshore wind project GEN-2015-032, Swisher CountyOnshore wind Β· 300 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem