πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Hornet Solar

Hornet Solar is a 602 MW solar request built and operating in the ERCOT interconnection queue, in Swisher County, Texas.

Queue statusOperating
  1. PlanningQueued Feb 2020 (completed)
  2. ConsentedDec 2021 (completed)
  3. Construction (completed)
  4. OperatingAug 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0021
Grid region
ERCOT (Texas)
Developer
Hornet Solar LLC
Connection point (POI)
tap 345kV 23914 Tule Canyon - 23912 Ogallala
Location
Swisher County, Texas
Technology
Solar: 602 MW
Total requested
602 MW
Study phase
IA
Queue status
Operational
Entered queue
3 February 2020
Agreement signed
6 December 2021
Proposed online date
October 2025
Came online
August 2024

Location

Marker shows the centre of Swisher County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Swisher County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem