United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Frye Solar

Frye Solar is a 502 MW solar + storage request built and operating in the ERCOT interconnection queue, in Swisher County, Texas.

Queue statusOperating
  1. PlanningQueued May 2018 (completed)
  2. ConsentedFeb 2021 (completed)
  3. Construction (completed)
  4. OperatingJul 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0080
Grid region
ERCOT (Texas)
Developer
Hecate Energy
Connection point (POI)
Kress sub KRSSW 23913 345 kV
Location
Swisher County, Texas
Technology
Solar: 502 MW · Battery
Total requested
502 MW
Study phase
IA
Queue status
Operational
Entered queue
16 May 2018
Agreement signed
6 February 2021
Proposed online date
July 2024
Came online
July 2024

Location

Marker shows the centre of Swisher County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Swisher County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem