SOLAR Β· ERCOT

BumbleBee Solar

BumbleBee Solar is a 212 MW solar request in interconnection study in the ERCOT interconnection queue, in Bee County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0412
Grid region
ERCOT (Texas)
Developer
BumbleBee Solar Farm LLC
Connection point (POI)
Tap 345kV 5725 PawneeSW5 - 8689 Tango
Location
Bee County, Texas
Technology
Solar: 212 MW
Total requested
212 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
27 February 2024
Proposed online date
July 2027

Location

Marker shows the centre of Bee County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Bee County