SOLAR + STORAGE · ERCOT

Honeycomb Solar SLF

Honeycomb Solar SLF is a 61.4 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Bee County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2021 (completed)
  2. ConsentedMay 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0559
Grid region
ERCOT (Texas)
Developer
Honeycomb Solar, LLC
Connection point (POI)
69 kV Tynan Substation (#8107)
Location
Bee County, Texas
Technology
Solar: 61.4 MW · Battery
Total requested
61.4 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
16 November 2021
Agreement signed
1 May 2023
Proposed online date
July 2026

Location

Marker shows the centre of Bee County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Bee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem