United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTHoneycomb Solar SLF
Honeycomb Solar SLF is a 61.4 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Bee County, Texas.
Queue statusConsented
- PlanningQueued Nov 2021 (completed)
- ConsentedMay 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Jul 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 22INR0559
- Grid region
- ERCOT (Texas)
- Developer
- Honeycomb Solar, LLC
- Connection point (POI)
- 69 kV Tynan Substation (#8107)
- Location
- Bee County, Texas
- Technology
- Solar: 61.4 MW · Battery
- Total requested
- 61.4 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 16 November 2021
- Agreement signed
- 1 May 2023
- Proposed online date
- July 2026
Location
Marker shows the centre of Bee County; the queue data does not give exact sites.
Other requests in Bee County
- Argenta SolarSolar + storage · 310 MW · agreement signed
- Foxtrot WindOnshore wind · 268 MW · agreement signed
- Abeja Solar FarmSolar · 201 MW · agreement signed
- Argenta StorageSolar + storage · 192 MW · agreement signed
- BumbleBee SolarSolar · 212 MW · in study
- Spinner Energy StorageBattery storage · 126 MW · in study
- Myers SolarSolar + storage · 102 MW · in study
- Myers StorageSolar + storage · 76.0 MW · in study
- Orchard Ray BESSBattery storage · 51.9 MW · in study
- Cuhullin WindOnshore wind · 310 MW · suspended
- Sparta SolarSolar · 252 MW · built
- Blackjack Creek WindOnshore wind · 241 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem