United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Abeja Solar Farm

Abeja Solar Farm is a 201 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Bee County, Texas.

Queue statusConsented
  1. PlanningQueued Dec 2024 (completed)
  2. ConsentedDec 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
27INR0372
Grid region
ERCOT (Texas)
Developer
Abeja Solar Farm LLC
Connection point (POI)
Tap 345kV 8012 PALADIO7A - 8689 TANGO7A
Location
Bee County, Texas
Technology
Solar: 201 MW
Total requested
201 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
19 December 2024
Agreement signed
16 December 2025
Proposed online date
September 2028

Location

Marker shows the centre of Bee County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Bee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem