United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTSpinner Energy Storage
Spinner Energy Storage is a 126 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Bee County, Texas.
Queue statusIn planning
- PlanningQueued Oct 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0083
- Grid region
- ERCOT (Texas)
- Developer
- GCI Wolf Energy Storage, LLC
- Connection point (POI)
- 8196 Poesta Substation 138kV
- Location
- Bee County, Texas
- Technology
- Battery: 126 MW
- Total requested
- 126 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 13 October 2023
- Proposed online date
- June 2027
Location
Marker shows the centre of Bee County; the queue data does not give exact sites.
Other requests in Bee County
- Argenta SolarSolar + storage · 310 MW · agreement signed
- Foxtrot WindOnshore wind · 268 MW · agreement signed
- Abeja Solar FarmSolar · 201 MW · agreement signed
- Argenta StorageSolar + storage · 192 MW · agreement signed
- Honeycomb Solar SLFSolar + storage · 61.4 MW · agreement signed
- BumbleBee SolarSolar · 212 MW · in study
- Myers SolarSolar + storage · 102 MW · in study
- Myers StorageSolar + storage · 76.0 MW · in study
- Orchard Ray BESSBattery storage · 51.9 MW · in study
- Cuhullin WindOnshore wind · 310 MW · suspended
- Sparta SolarSolar · 252 MW · built
- Blackjack Creek WindOnshore wind · 241 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem