United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTMesquite Creek Windpower Repower
Mesquite Creek Windpower Repower is a 213 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Dawson County, Texas.
Queue statusIn planning
- PlanningQueued Apr 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0501
- Grid region
- ERCOT (Texas)
- Developer
- Mesquite Creek Wind LLC
- Connection point (POI)
- <59900><Long Draw><345>
- Location
- Dawson County, Texas
- Technology
- Wind: 213 MW
- Total requested
- 213 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 29 April 2025
- Proposed online date
- December 2027
Location
Marker shows the centre of Dawson County; the queue data does not give exact sites.
Other requests in Dawson County
- Longview WindOnshore wind · 353 MW · agreement signed
- Red Holly SolarSolar + storage · 260 MW · agreement signed
- Red Holly StorageSolar + storage · 50.0 MW · agreement signed
- Red Holly Storage 1Solar + storage · 50.0 MW · agreement signed
- Fivemile WindOnshore wind · 282 MW · in study
- Green Holly SolarSolar · 414 MW · suspended
- Al Pastor BESSOther · 103 MW · built
- Lamesa Solar B (Phase II) IVORYSolar · 50.0 MW · built
- Blackwater Draw SolarSolar · 152 MW · withdrawn
- Gold Creek SolarSolar · 140 MW · withdrawn
- Atascosa I SolarSolar · 127 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem