United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTLamesa Solar B (Phase II) IVORY
Lamesa Solar B (Phase II) IVORY is a 50.0 MW solar request built and operating in the ERCOT interconnection queue, in Dawson County, Texas.
Request details
- Queue ID
- 16INR0023b
- Grid region
- ERCOT (Texas)
- Developer
- OCI Solar
- Connection point (POI)
- 1163 Lamesa 138kV
- Location
- Dawson County, Texas
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 26 June 2014
- Agreement signed
- 28 July 2016
- Proposed online date
- December 2018
- Came online
- December 2018
Location
Marker shows the centre of Dawson County; the queue data does not give exact sites.
Other requests in Dawson County
- Longview WindOnshore wind · 353 MW · agreement signed
- Red Holly SolarSolar + storage · 260 MW · agreement signed
- Red Holly StorageSolar + storage · 50.0 MW · agreement signed
- Red Holly Storage 1Solar + storage · 50.0 MW · agreement signed
- Fivemile WindOnshore wind · 282 MW · in study
- Mesquite Creek Windpower RepowerOnshore wind · 213 MW · in study
- Green Holly SolarSolar · 414 MW · suspended
- Al Pastor BESSOther · 103 MW · built
- Blackwater Draw SolarSolar · 152 MW · withdrawn
- Gold Creek SolarSolar · 140 MW · withdrawn
- Atascosa I SolarSolar · 127 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem