ONSHORE WIND · ERCOT

Longview Wind

Longview Wind is a 353 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Dawson County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2025 (completed)
  2. ConsentedDec 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
26INR0530
Grid region
ERCOT (Texas)
Developer
Longview Wind, LLC
Connection point (POI)
Venturi (Bus #59923)
Location
Dawson County, Texas
Technology
Wind: 353 MW
Total requested
353 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
22 September 2025
Agreement signed
16 December 2025
Proposed online date
December 2028

Location

Marker shows the centre of Dawson County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Dawson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem